• THE PROJECT
Titan implemented the initial development strategies and project budgets, including cash flow projections for the project. The next step was to market the center to the retailers. Once build-to-suit commitments were
obtained from Blockbuster and R&S Strauss Discount Auto for 75% of
the space, the project was ready to move ahead. To advance the project
forward, Titan provided the necessary construction financing. Titan was
also instrumental in securing the permanent loan commitment from
John Alden Insurance of Florida. Subsequently During the construction
phase Titan executed the 25,000 sqf. of demolition of an existing
building and interior and exterior construction of the shopping center.
PROJECT STATISTICS |
| Construction Type: |
New Construction |
| Building Type |
Commercial |
| Total Sq. Ft.: |
25,000 |
| Titan's Role: |
PM/CM |
| Project Cost: |
2.5MM |
| Client |
Ed Bloom |
| Start Date: |
1993 |
| Completion Date: |
1994 |
|